Contract Identification
Berbera International Airport (ITT/BBA/001) Refurbishment of Terminal Building & Related Facilities, Berbera.
Award Date, Implementation Period
April 2022
Completion Date
April 2024
Role in Contract
Main Contractor β
Management Contractor
Total Contract Amount
4,575,378 USD
If Partner in a JV, or Subcontractor, Specify Participation in Total Contract Amount
N/A
N/A
N/A
Roles and Responsibilities
The contractor responsibility consisted of complete rehabilitation of the airport, including comprehensive maintenance works for the passenger terminal and related facilities.
The work included interior and exterior finishing works, IT surveillance, service halls, support services, sound systems, control tower building, GSE facilities, GRP tank assembly, chainlink fence assembly, road construction, buildings, entrance gate, and fences.
Employer's Name
Berbera International Airport Company
Address
Berbera International Airport
Berbera, Somaliland
Telephone / Fax Number
+252 637340450
E-mail / Website
https://www.berbera-airport.com/
Amount
- Civil Works: 269,181.04 USD.
- MEP Works: 121,097.95 USD.
- Firefighting Works: 19,957.35 USD.
- Driveway: 53,656.00 USD.
- External Security Fence: 220,509.29 USD.
- Internal Security Fence: 310,350.00 USD.
- Water Filtration System: 21,000.00 USD.
- Current GSE Sheds: 9,438.93 USD.
- Old Cargo Building: 12,486.20 USD.
- Control Tower: 38,245.97 USD.
- Mobilization and Demolition: 40,000.00 USD.
Physical Size
- Refurbishment of the main terminal building with total area of 2010 mΒ².
- External and driveway works with total length of 2152 mΒ².
- External and internal security fence works with total length of 18,500 internal and 2,700 external.
- Installation of a water filtration system with total capacity of 200 people per day.
- Refurbishment of an old cargo building with total area of 1600 mΒ².
- Maintenance works for the control tower with 10.3 m height.
- Installation of a GRP tank with total capacity of 108 cmΒ³.
- Construction work for the main gate entrance of the airport, 7.3 m wide and 7.5 m height.
- Completion of electromechanical works for all buildings in the project.
- Completion of infrastructure works including water supply network, parking, and roads.
Complexity
- The works were carried out in different stages and places as the airport is over 4 kmΒ² in area.
- The project handled various additional works.
- Worked in a restricted area that required security and work permits.
- Incomplete designs and scope of work were specified at the start of the project.
Methods / Technology
Refurbishment, maintenance, and replacement works were carried out on various airport facilities using local labor, engineers, and technicians.
Construction Rate for Key Activities
- Civil works in the terminal.
- MEP works in the terminal.
- Firefighting works in the terminal.
- Driveway works.
- External security fence.
- Internal security fence.
- Water filtration system.
- Old cargo building works.
- Control tower works.
- Additional works.